Current Status Update
March 2021
Phase 1 – Geiger Boulevard – Hayford to Soda
Construction is complete with only minor cleanup and establishment work to be completed. Private development and third party utility work continues in the area.
Phase 2 – Geiger Boulevard – Soda to Grove/Flightline
Construction will resume the week of March 15th 2021, weather dependent. Geiger Boulevard will be closed from Soda to Grove/Flightline until the end of June 2021.
Local access routes to properties and businesses will depend on the location within the project limits. Properties located on Geiger and Electric West of the intersection of Geiger and Electric will access from the West using the Medical Lake Interchange, Geiger, Hayford, 53rd, Electric, Dowdy and Spotted. Properties on Geiger between Pilot and Grove/Flightline will access from the East using the Grove/Geiger Interchange. Local access will be maintained through the road closure.
Traffic control plans and a map showing the closures can be found attached at the bottom of this webpage. The traffic control plans were designed with two phases to close one section at a time, or both simultaneously. Both phases of the traffic control plans will be in place simultaneously.
November 2020
Phase 1 – Geiger Boulevard – Hayford to Soda
Construction is complete with only minor cleanup and establishment work to be completed. Private development and third party utility work continues in the area.
Phase 2 – Geiger Boulevard – Soda to Grove/Flightline
Construction began mid-August focusing on Soda to Electric. The roadway was paved back and work stopped for winter in mid-November. Work will resume in Spring 2021 when weather allows.
January 2020
Phase 1 - Geiger Boulevard - Hayford to Soda
Full-scale construction work was halted in November of 2019 to winter-over the project. Utility work that can be completed in cold weather has progressed over the winter months. Full scale construction will resume in the spring of 2020 to complete Hayford and Geiger intersection traffic signal, shared-use path, road widening East of Amazon improvements to Thomas Mallen Road and other outstanding work to complete the project.
Road widening from Thomas Mallen Road to Soda Road is underway by a Tax Increment Finance (TIF) project being constructed concurrently by a developer. This work is partially underway over the winter months but activity will increase in the spring of 2020.
Geiger Boulevard is currently closed between Thomas Mallen and Soda Roads. The detour utilized Electric Avenue, 53rd Avenue and Hayford Road. Access to properties and businesses along Geiger from Soda to Electric is open. Access to Amazon from Geiger is currently open via Thomas Mallen or Hayford, but Thomas Mallen will be closed intermittently as work progresses on Geiger until project completion.
Phase 2 - Geiger Boulevard - Soda to Grove/Flightline
Project Design is currently underway with construction and anticipated for the summer of 2020.
September 2019
The construction contractor will be closing both Geiger Blvd. and Hayford Rd., starting 9/30/2019. The closure is in conjunction with WSDOT's 10-day closure of west bound I-90 interchange at the Medical Lake exit. Detour routes for the area can be found here. Local access for residents and businesses will be maintained primarily on Hayford Rd.
Following these closures, Hayford Rd. north of Geiger improvements will be complete and re-opened to traffic while work continues on Geiger, east of Hayford.
July 2019
Spokane County Public Works opened bids for the Geiger Boulevard - Hayford Road to Soda Road Project on June 26th, 2019. Shamrock Paving Inc. was the low bidder and has been awarded the contract. Work is anticipated to begin the end of July / early August and continue through November 2019.
Posted by: wendyposeelyoa.blogspot.com
Source: https://www.spokanecounty.org/4151/Geiger-Boulevard-Infrastructure-Improvem
Posting Komentar untuk "Road Construction Jobs Spokane Wa"